Comment on Atherton spent $145K to delay train electrification. The rest of us paid $400Mparent

Comments

The article's somewhat dubious argument is that the 2012 budget estimate was $1.5B, the actual cost by 2017 was $1.9B, and the $400M difference was caused entirely by Atherton's law suit.

Which is obviously a bit sus, because the actual lawsuit froze everything for only around 18 months from Feb 2015 to Sep 2016.

The CBOSS fiasco, which added $200 million in costs, certainly can't be blamed on Atherton.

Reasonable to think agencies involved would wait for the outcome of the lawsuit to act, no? So those 3 years in limbo were likely also attributable.

there was also a delay in the decision for funding until may 2017. that's another 8 months. but then we don't know when that decision would have been made originally.