Is there a AI data center construction process that doesn't involve these costs?

Is there a large scale construction project that doesn’t incur these costs? Is the AI data center substantially worse on these metrics that other comparable projects? Or are we talking about it only because it’s AI-related?

Or are we talking about it only because it’s AI-related?

We're absolutely only talking about it because it's AI.

From about 5 minutes of digging, I found the below which perhaps helps to put the 29m gallons in context.

The Fayette County Water System has a total production capacity of 22.8 million gallons per day (MGD).

Source: https://fayettega.org/doing-business/global-access-infrastru...

So...keeping things simple and using 30d months:

Using 29M gallons over 15 months = 29,000,000 / (15 * 30) = 64,444 gallons per day avg

Based on 22.8m daily production capacity that's less than 0.3% of the total production capacity per day.

(Happy to be corrected if my napkin maths is wrong / i'm missing something here!)